Message ID: 0000000000000000000000073_001


ID73
Market Participant NameStadtwerke Kiel AG
Market Participant Typeeic
Market Participant ID1
Message ID0000000000000000000000073_001
Event StatusInactive
Type of EventProduction unavailability
Event Start2020-10-06 10:00:00
Event Stop2020-10-06 10:25:00
Type of UnavailabilityPlanned
Publication date/time2020-10-06 08:55:01
Unit of MeasurementMW
Unavailable Capacity25.00000
Available Capacity165.00000
Installed Capacity190.00000
Reason of the Unavailabilityoutage / maintenance
Remarks
Fuel TypeFossil Gas
Bidding Zone10XDE-EON-NETZ-C
Affected Asset NameKüstenkraftwerk Kiel
Affected Asset EIC11W0-0000-0163-M
StatusSaved and Published
Created at06.10.2020 8:55:01
Updated at06.10.2020 10:25:01
Showing 1-1 of 1 item.
IDMessage IDStatusMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
 
 
×
×
 
×
 
 
730000000000000000000000073_001PublishedStadtwerke Kiel AGInactiveProduction unavailability2020-10-06 10:00:002020-10-06 10:25:00Planned2020-10-06 08:55:01MW25.00000165.00000190.00000Fossil Gas10XDE-EON-NETZ-CKüstenkraftwerk Kiel